U District Station is about 80 feet deep, and Sound Transit stations are only set to get deeper and more cavernous in the next round of Seattle expansions. This is contributing to cost issues. (Doug Trumm)

Shrinking station footprints could help avert light rail project delays.

Sound Transit 3, the region’s most ambitious transit expansion ever, is facing a mounting cost crisis. Project budgets have grown far beyond the original estimates, threatening to derail the entire program. With an increasingly uncertain federal funding environment, Sound Transit must find ways to dramatically reduce costs or risk leaving promised transit lines unbuilt.

Stations represent the largest share of urban rail transit’s construction costs. Elevated stations are generally about twice as expensive as surface stations, while underground stations are about four times as expensive. Reducing the costs of underground stations, therefore, has an outsized impact on overall project costs. 

In 2024, New York University’s Transit Cost Project released a case study that attempted to identify why the first phase of the Second Avenue Subway extension in New York City, completed in 2017, cost several times the cost of similar projects in Europe. They found that stations were both nearly twice as long as those found in European projects and twice as long as earlier designs for the same project in the 1970s. In particular, the Transit Cost Project found that “French, Swedish, and Italian subway station digs are barely longer than the trains they intend to serve; an excess of 5% is typical, and 20% is high.” 

Armed with these findings, recent reporting by Nolan Hicks of NYU’s Marron Institute found a repeat of this error in designs for the next expansion phase. The Metropolitan Transportation Authority (MTA) has since designed smaller stations for the second phase of the Second Avenue Subway, generating over $300 million in cost savings.

Side view of MTA station design in 1970s versus today
MTA’s $1 billion station includes copious excess space not necessary for the platform and circulation needs of riders. (Source: NY Post)

In light of the Transit Cost Project’s findings, this article will examine all of Sound Transit’s underground light rail stations, both already built and planned in Sound Transit 3 (ST3). Overbuilding and overdesign were already present from the construction of the Downtown Seattle Transit Tunnel (DSTT) through Sound Transit 2 (ST2). These problems have only worsened in ST3, with a dramatic increase in the size, depth, and complexity of stations compared to ST2. 

There is a massive opportunity, then, to save hundreds of millions of dollars by following the MTA’s lead with right-sizing station designs. Taking advantage of these and other opportunities will require a systemic rethink of how Sound Transit designs stations and enabling state legislation.

If you support this effort, please send a letter to the Sound Transit Board.

Trend toward increasing station length, width, and depth

Station sizes have increased with each phase of expansion from Central Link’s repurposed DSTT to ST3. Stations are getting increasingly long relative to the required platform space.

  • Sound Move Stations (DSTT only): 50% longer and 50’ – 60’ deep (Table 3) 
  • ST2 Stations: 43% longer and 75’ deep on average (Table 2) 
  • ST3 Stations: 79% longer and 108’ deep on average (Table 1)
  • New Standard Underground Station (cut-and-cover): 45% and 90’ deep

These station length numbers are greatly in excess of the maximum 20% figure found in France, Sweden, or Italy. The implications of size on cost are even greater given mined construction is proposed for Midtown and Westlake Center. NYU’s Transit Costs Project found mined stations cost 1.5 times more on a per volume basis than cut and cover on the 2nd Avenue Extension. 

Note: All station lengths are based on Environmental Impact Statement documents due to information accessibility and comparison consistency – final design length and profile may deviate from those presented here. Sound Move stations were calculated based on the Washington State Department of Natural Resources’ Engineering Geology of the Downtown Seattle Transit Project.

Table 1: Sound Transit 3 Underground Stations

Sound Transit 2 Underground StationsPercent Longer than Platform (380’)Depth (feet)Construction Method
West Seattle Junction 50%70’Cut-and-cover
Midtown Station85%140’Mined
Westlake 40%135’Mined
Denny 190%100’Cut-and-cover
South Lake Union 30%120’Cut-and-cover
Seattle Center 80%85’Cut-and-cover
ST3 underground stations, avg.79%108’N/A
Source: Sound Transit, Table by Trevor Reed
**International District Station alternatives complexity and number of competing alternatives.

Gallery: Sound Transit’s ST3 Underground Station Designs

Table 2: Sound Transit 2 Underground Stations Sideview 

Sound Transit 2 Underground StationsPercent Longer than Platform (380’)Platform Depth (feet)Construction Method
Roosevelt 50%65’Cut-and-cover
U District 40%75’-85’Cut-and-cover
University of Washington*40%95’Cut-and-cover
Capitol Hill40%65’Cut-and-cover
ST2 underground stations, avg.43%75’N/A
*Crossover tracks present, exact % not calculable

ST2 Stations Longitudinal View

  • Roosevelt Station Side View
  • U District Station Side View
  • Capitol Hill Side View
  • UW Station Side View

Table 3: Sound Move Underground Stations

Central Link StationsPercent Longer than Platform (380’)DepthConstruction Method
Westlake50%50-60’Cut-and-cover
Symphony50%60’-70’Cut-and-cover
Pioneer Square50%60’-70Cut-and-cover
Beacon HillInformation Unavailable160’Mined

Station width and excavations to support passenger movement between the surface and platform also dramatically increased from ST2 to ST3. Each ST2 underground station features access that fits largely within the station box. If access does extend beyond the station box, it occurs close to the surface before returning to the space generated from the station box excavation. The massive ancillary spaces (dark green) are a testament to the excesses of ST3’s bloated station design. 

ST2 stations fitting within the station box

  • Roosevelt Station Cross Section
  • University of Washington Station Cross Section
  • Capitol Hill Station Cross Section
  • U District Station Cross Section

ST3 dramatically expands station boxes and excavations for access compared to ST2

An international perspective

Sound Transit stations, both existing and proposed, are significantly larger than completed or under-construction stations in Paris, Milan, and Rome. 

The three station profiles below are from the Paris Metro Line 14 extension that opened in June 2024. They feature minimal excavations beyond the platform length and width and efficient use of excavated space for vertical conveyance. Most station access is provided within the station box.

Paris’ Line 14 stations longitudinal view

Paris’ Line 14 stations cross-sectional view

Rome Fori Imperiali Station construction

Rome Line C Forzi Imperiali
Rome Line C Forzi Imperiali Station cross section shows efficient design in a complex location. (Metro de Roma / We Build Group)

Rome’s incredible Fori Imperiali Station is being constructed within an active archaeological site, incorporating artifacts and excavations unearthed during construction to create a ‘museum station.’ The contextual challenges faced by Italian engineers of maintaining the integrity of a 2,000-year-old archaeological site are surely equivalent to or greater than those found in Seattle. Yet, the station remains shallower, smaller and more efficient than stations proposed by Sound Transit in far simpler locations.

America is an anomaly, having largely stopped building rail transit between the Great Society metro systems of the 1960s and the recent boom in the late 90s inspired by Portland’s MAX and LA Metro. Even worse, many systems faced a generation of neglect and decline, epitomized by New York MTA’s financial crisis. Where European and Asian countries continued building, learning, and innovating across borders, America spent a generation triaging and stabilizing. Sound Transit and American transit builders overbuild and overdesign for three primary reasons: design inertia, over-interpretation of design codes, and stakeholder-driven design. 

America’s inertia by design

The United States’ foremost national reference for underground construction is the New York Metro. One design feature that Sound Transit has uncritically copied from New York are full-length or oversized mezzanines. These can be necessary to accommodate transfers or massive passenger flows, but do not reflect Link’s needs or modern design practices. New York has recognized its own stations’ size issues, but still exhibit major shortcomings in designs.

This design inertia is reflected in Sound Transit’s new standard underground station configuration, which is 45% longer than the platform (image below). The standard design was drafted in response to expert feedback gathered from the agency’s Technical Advisory Group (TAG). Recommendation #5 urged Sound Transit to create optimal designs, but the oversized standard that resulted provides strong evidence for an institutional bias for large stations.

Sound Transit Standard Underground Station Side View
Sound Transit has sought to standardize station design, but its standard still includes excess excavation. (Sound Transit, markup by Trevor Reed)

Milan’s Lines 4 and 5 provide a contrast in vertical access space efficiency compared to Sound Transit’s standard design. By utilizing vertical space efficiently, they reduce excavation and construction needs while improving user experience.

Milan Lines 4 and 5 – Deep stations with efficient access

  • Milan Line 4 Station Cross Section
  • Milan Line 4 Station Cross Section
  • Milan Line 4 Station Cross Section
  • Milan Line 4 Station Cross Section
  • Milan Line 4 Station Cross Section
  • Milan Line 5 Station Cross Section

Overinterpretation of codes

Sound Transit has encountered challenges with inconsistent code interpretation, such as when the City of Bellevue interpreted the national fire code contrary to typical practice. However, Sound Transit’s own standard interpretation is likely more rigorous than global norms. A review of fire code interpretation in Canada, for instance, found major deviations in interpretation compared to European practice. An assessment of new American transit infrastructure would likely generate similar findings. Given the intended universality of the National Fire Protection Association’s NFPA 130 standards, divergence in application makes little sense.

Stakeholder input

Sound Transit is actively working on curtailing stakeholder-driven design by introducing standardized designs. Stakeholders are any party that can exert influence over the process. It can range from employees wanting more break spaces, to what construction methods are used to how stations are integrated into a neighborhood. This often takes the form of local jurisdictions leveraging their powers, both real and perceived, to shape outcomes.  

How can Sound Transit design stations more efficiently?

Sound Transit is undertaking an agency-wide realignment to address the increasing costs and delay of delivering the Sound Transit 3 (ST3) extensions. This process is already bearing fruit. Improvements in project delivery, demoed on West Seattle Link, could result in hundreds of millions in savings from design to construction. Adopting Reference Class Forecasting has massive potential to reduce overdesign and overbuilding.

Reference class forecasting (RCF)

Reference class forecasting or RCF is a project management framework that prioritizes creating a distribution of similar projects and analyzing project elements relative to each other, in order to hone project designs and more accurately anticipate costs. It won Daniel Kahneman a Nobel Prize and is broadly applied to transportation, most notably by Bent Flyvbjerg

RCF can help agencies curtail design inertia, overinterpretation of design codes, and stakeholder-led design. A project library where drivers of cost and risk are classified creates the opportunity to address them systematically – a standard-optimized formula for delivering transit infrastructure.

While Ballard Link does face engineering challenges, the excessive size and depth of West Seattle Junction station particularly reveals signs of scope creep and affirms the needs for RCF. The station is deeper, wider, and longer than cut-and-cover station proposals developed for Rainier Valley in the late 90’s (images below) let alone foreign peers.

Why is a station now 70 feet deep when contextually similar stations 20 years ago were 40’ (and why is the new standard cut-and-cover station design 90 feet)? Why are 34-foot wide platforms now standard when 24 feet used to suffice? What are the benefits of these larger and deeper stations? Given excavation costs increase exponentially with depth due to a change in the reinforcing necessary, any reduction in depth for proposed cut-and-cover stations would have a similar impact on reducing costs.

Sound Transit’s increasing station depth from Sound Move to Sound Transit 3

  • West Seattle Junction Station Cross Section
  • Rainier Cut-and-Cover Station 40' Deep
  • Rainier Cut-and-Cover Station 40' Deep
  • Cut-and-Cover Versus Mined Station Cost - Rainier Alternative

RCF reduces the potential for size and design creep by creating a clear design decision criteria and establishing a body of evidence on the tradeoffs. Additionally, it would directly support the first recommendation of the Technical Advisory Group to “Rebuild trust and clarify the roles and responsibilities of the ST Board and staff.” The board historically inserted themselves too deeply into project development, while Sound Transit did not provide specific recommendations or solutions. What better way to build trust than to generate recommendations with a supporting body of evidence?   

Since underground stations are the riskiest and most expensive hard cost, they have the greatest potential benefit from RCF-based re-engineering. Nonetheless, the lessons to be learned are broadly applicable to other projects.

Sound Transit should complete the following:

  • Undertake detailed analysis of station and guideway design elements in comparison to other projects globally, including non-English speaking countries.
    • Systematically work to reduce station size, depth, and complexity based on best practice applications of codes and design standards in the creation of standard station designs.
    • Establish clear, objective criteria to decide between elevated, at-grade, trenched, or tunneled alignments.
    • Establish clear, objective criteria on construction methods employed, prioritizing quickest and least expensive/risky methods.
  • Apply the aforementioned retroactively to projects in design and planning and establish defendable estimates for project time, cost, and quality.
  • For future projects, Sound Transit should build reference classes for service-based planning and the corresponding infrastructure necessary to meet needs. 

Leveraging RCF to reduce station size and complexity based on the experiences of global leaders presents a major opportunity to reduce the time and cost of construction, while increasing access to information for board members to make informed decisions. Applying these learnings broadly to planning other design decisions promises to create a sustainable basis for innovation and improvements.

Code preemption and permit expedition

Local jurisdiction discretion over Sound Transit station design standards makes no sense. Similarly, complying and obtaining permits across jurisdictions with diverse incentives and objectives unduly burdens construction. Seattle Councilmember Maritza Rivera’s recent aborted proposal adding red tape illustrates the uncertainty and arbitrary burdens any local jurisdiction can create.

Sound Transit should:

  • Ask the State for the power to self-approve design decisions, or enter into joint delivery with the Washington State Department of Transportation to leverage their powers as a State agency to reduce exposure to local jurisdictions. 
  • Ask the State to streamline permitting for transit projects by imposing deadlines on third parties for compliance – California has embarked on this reform via SB 445, which passed out of their state senate in a recent 34-1 vote.

Developing reference classes for station and guideway design to prevent over-compliance and stakeholder driven design will only work if Sound Transit has the power to execute. 

A path forward, starting with underground stations

Underground station depth and size are a primary contributor to the exorbitant costs West Seattle/Ballard Link are experiencing. New York’s MTA offers an example for dramatically reducing costs, but Sound Transit must go further. 

Achieving CEO Constantine’s goal for realignment, to “rethink the way we plan and we provide board members with the tools to drive the agency forward,” while developing alternatives to “scope and schedule” changes requires innovation and reform. 

Developing reference class forecasting is an opportunity to work systematically to reduce cost and delivery times. Empowering this approach requires the state giving Sound Transit the authority necessary to pursue innovation and curtail stakeholder abuses via code preemption and permitting powers. This crisis is an opportunity Sound Transit cannot afford to miss.

If you agree please sign our letter to the Sound Transit Board.

Transportation Reform is a volunteer-run advocacy group dedicated to reforming processes that cause expensive, delayed, and inadequate transportation projects. If you are interested in joining our coalition, please contact trevor@transportationreform.org.

Article Author

Trevor Reed is a transportation planner who lives in Mercer Island and represents the East-King Subarea on the Sound Transit Community Oversight Panel. He completed his Master's degree at the Bartlett School of Planning focusing on large project delivery and worked as a researcher at the Omega Center: Center for Mega Infrastructure and Development. Currently, Trevor works in transportation data analytics focusing on road safety and network efficiency. His work concerning the impacts of traffic congestion on cities has appeared nationally in the New York Times, Wall Street Journal, and PBS's Nightly Business Report. He co-founded the advocacy group Transportation Reform.