East Link can be seen snaking along the side of the I-90 floating bridge starting on the left. Light rail is headed to Mercer Island, Bellevue and ultimately Redmond. The Bellevue skyline dots the horizon. (Photo by Doug Trumm)

Sound Transit offered transit nerds a treat this Halloween as it posted an update on East Link construction, complete with pictures. The line continues to be on schedule for a 2023 opening. 2.1 million labor hours have been logged already building East Link–or the Blue Line as it will be in Sound Transit’s map.

Phase one of the East Link extension is 14 miles long with 10 stations, bringing Redmond, Bellevue, Mercer Island, and the Judkins Park neighborhood of Seattle into the fold of regional light rail service. By 2026, the Blue Line will serve 43,000 to 52,000 daily riders, Sound Transit projects.

“Trips between downtown Bellevue and Westlake Station in downtown Seattle will take 24 minutes, no matter how bad traffic is,” Katie Metzger of Sound Transit wrote.

Map shows East Link will reach Redmond Technology Center by 2023 and extend to Downtown Redmond in 2024. (Sound Transit)
East Link will reach Redmond Technology Center by 2023 and extend to Downtown Redmond in 2024. (Sound Transit)

Booming Bellevue Downtown

In the blog post, Metzger also noted it’s not just light rail construction, neighborhoods near East Link stations are brimming with mixed-use development as well, which make cameos in some of the photos. Downtown Bellevue is the epicenter of the Eastside boom–and it recently got an upzone to 60 stories and its own Amazon towers–but Wilburton and the Spring District are also redeveloping rapidly.

Downtown Bellevue looms in the background above the guideway leading up to Wilburton Station. (Sound Transit)
Downtown Bellevue looms in the background above the guideway leading up to Wilburton Station. (Sound Transit)

I recently covered now Northgate Link (opening in 2021) is sparking a building boom in North Seattle around U District Station, Roosevelt Station, and Northgate Station. Similar things are happening around some of the East Link stations–and we will run down how those station areas are developing in future articles.

East Main Subway

Workers in the tunnel under downtown Bellevue, which stretches from East Main Station to Bellevue Downtown Station. (Sound Transit)
Workers in the tunnel under downtown Bellevue, which stretches from East Main Station to Bellevue Downtown Station. (Sound Transit)

East Main is where East Link enters a tunnel to make it north through dense office land and reaches Downtown Bellevue Station. It is going to be a dense neighborhood and likely a busy station. It’s already a residential focal point with access to Bellevue’s Downtown Park–Bellevue should play up that main street feel.

Wilburton Spans I-405

Elevated guideway to Wilburton with Bellevue skyline in background. Progress as of fall 2018. (Sound Transit)
Elevated guideway to Wilburton with Bellevue skyline in background. Progress as of fall 2018. (Sound Transit)

From Downtown Bellevue, East Link jogs east to Wilburton crossing I-405 and a sea of parking. Bellevue is planning a big transformation here called Grand Connection, finally grappling with the scar that I-405 gashed through the city. Bellevue is considering a freeway lid and pedestrian overpass to reconnect Wilburton to Downtown. Wilburton Station already has Overlake Medical Center and Bellevue’s Uwajimaya market closeby, but it’s likely to get some major infill redevelopment and the City of Bellevue is working on an upzone to support urban density.

Spring District Blooms

Next stop to the northeast, the Spring District is anchored by a 36-acre master-planned community two stations past Downtown Bellevue. NBBJ and Wright Runstad collaborated on the plan, which emphasizes office space, but does include some housing too. Outdoor recreation company REI is building a new Spring District headquarters.

REI's new headquarters is the backdrop for this shot of Spring District Station. (Sound Transit)
REI’s new headquarters is the backdrop for this shot of Spring District Station. (Sound Transit)

Bel-Red Buds

Bel-Red elevated guideway progress from fall 2018. Girders are in place. (Sound Transit)
Bel-Red elevated guideway progress from fall 2018. (Sound Transit)

Bel-Red Station is also expected to see a dramatic redevelopment although that’s mostly in its infancy right now. The Bel-Red corridor got a rezone topping out at 12 stories, and some builders are predicting it could be “the next South Lake Union.” That may be an exuberant claim, but certainly it won’t be almost exclusively big-box retail, strip malls, and warehouses much longer.

Overlake is Next to a Freeway

Overlake Station. (Sound Transit)
Overlake Station. (Sound Transit)

The station shape is firming at Overlake Village, which is already a transit hub for the area and has some dense mixed-use buildings intermixed with the drive-throughs.

Microsoft Makeover at Redmond Technology Center

Redmond Technology Center will serve Microsoft's sprawling campus. (Sound Transit)
Redmond Technology Center will serve Microsoft’s sprawling campus. (Sound Transit)

Redmond Technology Center is currently dominated by its parking structure, but this is the gateway to Microsoft’s massive 500-acre corporate campus. This summer Microsoft announced a major overhaul of its campus, adding two million additional square feet of office space–room for 8,000 additional employees. The Redmond campus already hosts most of Microsoft’s 51,000 workforce in the Seattle area. Acknowledging the impact it has on area housing prices, Microsoft pledged $500 million to boost affordable housing creation–which is better than I can say about Amazon, which prefers million-dollar PAC donations to philanthropy or corporate social responsibility.

A rendering of Microsoft's updated campus, which borders Redmond Technology Center Station. Click to enlarge. (Credit: Microsoft)
A rendering of Microsoft’s updated campus. Click to enlarge. (Credit: Microsoft)

That plan hopes to address how difficult it is to navigate within the car-centric campus. It takes about 22 minutes to walk from one edge of the campus of the campus to the other, and much of that isn’t pleasant given heavy car traffic. A new skybridge over SR-520 will connect the east and west portions, which, along with open spaces and a denser footprint, hopes to create a more pedestrian and bike-friendly setup. Some of the original buildings have already been demolished. The campus update is expected to be completed in 2022 and 2023–just before East Link opens.

Downtown Redmond Extension Breaks Ground

12 officials exercise their shovel arms in this posed photo for the groundbreaking for the Downtown Redmond Link Extension. (Sound Transit)
The Eastside 12 exercise their shovel arms. (Sound Transit)

Also in the news this month: Sound Transit broke ground on the Downtown Redmond extension. As if recreating the Last Supper, 12 officials lined up to pose. One can see why they’re excited though. Downtown Redmond will only have to wait one more year after East Link opens to get light rail.

A View of South Bellevue

An aerial shot of South Bellevue Station shows it's surrounded by woods and the Mercer Slough. (Sound Transit)
An aerial shot of South Bellevue Station shows it’s surrounded by woods and the Mercer Slough. (Sound Transit)

South Bellevue wasn’t on yesterday’s photo tour, but it was in a photo tour from last year. Sandwiched near the Mercer Slough, it’s not the most urban setting. Quaint and separately incorporated Town of Beaux Arts Village is to the west, and the West Bellevue neighborhood does have some large apartment buildings to the north, but it will be interesting to see what, if anything, grows up around this station. The 1,500-stall parking garage might be the largest structure for a while.

From November 2018: "Looking south from the platform at the South Bellevue Station. Note the columns where the train guideway will rise above traffic on Bellevue Way Southeast." (Sound Transit)
From November 2018: “Looking south from the platform at the South Bellevue Station. Note the columns where the train guideway will rise above traffic on Bellevue Way Southeast.” (Sound Transit)

Not to Be Forgotten Mercer Island

Yesterday’s Sound Transit photo tour didn’t include Mercer Island. But Seattle Transit Blog‘s Bruce Englehardt (a prolific Wikipedia contributor under the moniker SounderBruce) has them covered. Below is the progress as of October 2017.

Mercer Island Station progress as of October 2017. East Link opens in 2023. (Credit: SounderBruce, Wikimedia Commons)
Mercer Island Station progress as of October 2017. East Link opens in 2023. (Credit: SounderBruce, Wikimedia Commons)

Here’s what Mercer Island Station looked like by August 2019.

Mercer Island Station is in the median of I-90. (Sound Transit)
Mercer Island Station is in the median of I-90. (Sound Transit)

On either side of Mercer Island, East Link must do an impressive engineering feat: running trains on a floating bridge that does jostle some in the wind. Sound Transit designed a new system to deal with this undulating surface. Mercer Island, home of Seattle Times publisher Frank Blethen–the region’s biggest defender of single-family zoning–surprise, hasn’t really embraced an urban makeover in advance of light rail’s arrival beyond a small area near the transit center. There is at least one new large mixed-use project planned near the station, though.

East Link runs on the I-90 floating bridge on special tracks to adjust for rocking motion. (Sound Transit)
East Link runs on the I-90 floating bridge on special tracks to adjust for rocking motion. (Sound Transit)

It’s too bad too since Mercer Island has an extensive freeway lid (they got it by threatening to block the freeway project and the state transportation department was more responsive to White and wealthy Mercer Island rather than Black and working class Central District that tried the same). Mercer Island’s lid creates a nice environment despite proximity to a freeway.

Judkins Park is Picking Up Steam

Finally, East Link does add one station in Seattle: Judkins Park. Like Mercer Island, this station is in the median of I-90, but development is still picking up on either side. The Mountains to Sound Greenway does snake along both stations, and I snapped this photo while biking along it this summer.

Judkins Park Station will straddle I-90 between Rainier Avenue and MLK Way. (Photo by author)
Judkins Park Station will straddle I-90 between Rainier Avenue and MLK Way. (Photo by author)

Judkins Park’s proximity to Seattle’s downtown core means it was already starting to heat up, light rail or no. One example is a 769-home complex to the south called Grand Street Commons. 200 of those in the south building will be affordable housing operated by Mt. Baker Housing Association, while Mandatory Housing Affordability will require significant contributions from the rest of the complex.

Grand Street Commons is two blocks south of Judkins Park Station and expected to break ground late in 2020 or in 2021 and likely open ahead of East Link light rail. (Credit: Runberg Architecture)
Grand Street Commons is two blocks south of Judkins Park Station and expected to break ground late in 2020 or in 2021 and likely open ahead of East Link light rail. (Credit: Runberg Architecture)

We’ll have more on station area development along East Link, so stay tuned.

Article Author
Publisher | Website

Doug Trumm is publisher of The Urbanist. An Urbanist writer since 2015, he dreams of pedestrianizing streets, blanketing the city in bus lanes, and unleashing a mass timber building spree to end the affordable housing shortage and avert our coming climate catastrophe. He graduated from the Evans School of Public Policy and Governance at the University of Washington in 2019. He lives in East Fremont and loves to explore the city on his bike.